Engineering Notes Archives - OnlineEngineeringNotes https://onlineengineeringnotes.com/tag/engineering-notes/ A Complete Guide to future Engineers Wed, 23 Apr 2025 07:07:41 +0000 en-US hourly 1 https://wordpress.org/?v=6.8 Valuation in Civil Engineering https://onlineengineeringnotes.com/2025/04/23/valuation-in-civil-engineering/ https://onlineengineeringnotes.com/2025/04/23/valuation-in-civil-engineering/#respond Wed, 23 Apr 2025 07:07:40 +0000 https://onlineengineeringnotes.com/?p=1715 1.1 Introduction Valuation is the technique of estimating or determining the fair price or value of a property such as building, factory, other engineering structure of various types of land etc. 1.2 Purpose of valuation 1.3 Terms used in valuation 1. Value and cost 2. Book value 3. Assessed value 4. Distressed value or forced ... Read more

The post Valuation in Civil Engineering appeared first on OnlineEngineeringNotes.

]]>
1.1 Introduction

Valuation is the technique of estimating or determining the fair price or value of a property such as building, factory, other engineering structure of various types of land etc.

1.2 Purpose of valuation

  • Buying or selling of property.
  • For mortgage as security of loan.
  • For determination of rent.
  • For tax fixation or assessment of taxes.
  • For compulsory acquisition.
  • For fixation of insurance premium.
  • To determine speculation i.e. more than fair price in selling.
  • To determine betterment charges i.e. more than fair price in buying.

1.3 Terms used in valuation

1. Value and cost
  • Value is the present market value of any property which may be higher or lower than cost of construction.
  • Cost means actual cost of construction.
2. Book value
  • It is original investment shown in account book of a company on its asset including properties and machinates.
  • Book value is applicable on building and movable properties but not on land.
  • Book value = Original cost – Total depreciation upto previous year
3. Assessed value
  • Value of any property recorded in record of local authority which is used for the purpose of determining the various taxes to be collected from owner of the property.
4. Distressed value or forced sale value
  • When a property is sold at a lower price than the market value of that time it is called distress value.
5. Replacement value
  • Value of property or its services calculated on the prevailing market rate to replace the same.
6. Retable value
  • Net annual letting value property which is obtained after deducting the amount of yearly repairs from gross income. Municipal and other taxes are charged on the rotable value of property.
7. Potential value
  • Some property like land has an inherent value which may go on increasing due to passage of time or can fetch more return if used for some alternative purpose. This inherent value is known as potential value.
8. Annuity
  • Annual periodic payment for repayment of the capital amount invested in a property or in some other form of investment by a party.
9. Perpetual annuity
  • If the payment of annuity continues for indefinite period, it is known as perpetual annuity.
10. Different annuity
  • If the payment if annuity begins at some future data after a number of years this is known as different annuity.
11. Scrap value
  • Dismantled material value of property at the end of its utility period.
  • 10% of cost of construction in case of building.
12. Salvage value
  • Value of any property at the end of utility period without being dismantled.
13. Gross income
  • Total income from all sources without deducting the outgoing necessary for operation, taxes, maintenance, replacements etc.
14. Outgoing
  • These are the expenses incurred to maintain the property by undertaking periodic repairs.
  • Also, includes government tax, sinking fund, management or collection charge other miscellaneous charges.
15. Net income
  • Amount left after deducting all outgoing, operational and collection expenses from gross income. i.e. Net income = Gross income – Outgoings
16. Capitalized value
  • Amount of money whose interest at the highest prevailing rate of interest will be equal to the net income from the property in perpetuity. i.e. CV = Net income * Year purchase (Y.P)
17. Years Purchase (Y.P)
  • Capitalized value required to be invested in order to receive an annuity of Rs. 1 at the prevailing rate of interest. i.e. Year’s purchase = 100 / Rate of interest
18. Sinking funds
  • It is a fund which is built up for sole purpose of replacement or reconstruction of a property when it loses its utility either at the end of its life span.
  • S = (Sn * R)/(1+R)n-1

Where,

S = Year installment of sinking fund

Sn = Sinking fund to be accumulated in n years

R = Rate of interest

n = Utility period / Life of property

19. Depreciation
  • The gradual decrease or loss in value of a property because of constant structural deterioration, use, wear and tear, decay etc.

1.4 Method of Determining value of property

1. Rental Method
  • In this method the rental income is calculated after deducting all outgoing from the gross rent, years purchase is calculated after adopting the current bank interest and then capitalized value of the property is worked out.
2. Profit based Method
  • Similar to rental method.
  • In this method the net profit is worked out after deducting all possible outgoing and years purchase calculated after adopting current bank interest rate and multiplied by YP to get capitalized value of property.
3. Cost based Method
  • In this method the actual cost incurred in constructing the building or in processing the property is taken as basis to determine the value of property.
4. Development based Method
  • This method of valuation is used for properties which are in the development stage or party developed stage.
5. Depreciation Method
  • Depreciated value of building is directly calculated with the help of formula

i.e. D = P [(100 – rd)/(100)]n

Where,

D = Depreciated value

P = Cost of building

rd = Rate of depreciation

n = No. of years

6. Plinth area Method
  • In this method the resent plinth area rate of similar building in the same locality with the same specification is worked out, multiplied with the plinth area of building whose valuation is to be done and suitable depreciation is allowed.
7. Capital value comparison Method
  • In this method, capitalized value of the property is worked out by direct comparisons with other capitalized value of similar property in the same locality, whose sale records are available.

1.5 Methods of valuation

  • After doing all the valuation works the valuation report is prepared for submitting in the concerned department.
  • The valuation report is divided into three parts:
    • Part I: Detail about property
    • Part II: Valuation calculation
    • Part III: Valuation declaration

Report format:

  • Cover page
  • Table of content
  • Valuation certificate
  • Description of the property
  • Appendix:
    • Introductory details
    • Technical details
    • Area calculation
    • Land value
    • Land ownership certificate
    • Citizenship certificate
    • Drawings
    • Photographs

References:

  • Dutta, B.N. – Estimating and Costing in Civil Engineering, UBS Publishers, New Delhi.
  • CPWD (Central Public Works Department), India – Standard Schedule of Rates and Analysis of Rates.
  • IS 1200 – Indian Standard for Method of Measurement of Building and Civil Engineering Works, Bureau of Indian Standards (BIS).
  • Punmia, B.C. – Estimating and Costing, Laxmi Publications.
  • Building Estimation and Costing Notes – Department of Civil Engineering, Pokhara University.
  • MoUD Nepal – Standard Norms and Guidelines for Public Infrastructure Development Projects.

The post Valuation in Civil Engineering appeared first on OnlineEngineeringNotes.

]]>
https://onlineengineeringnotes.com/2025/04/23/valuation-in-civil-engineering/feed/ 0
Rate Analysis in Civil Engineering https://onlineengineeringnotes.com/2025/04/22/rate-analysis-in-civil-engineering/ https://onlineengineeringnotes.com/2025/04/22/rate-analysis-in-civil-engineering/#respond Tue, 22 Apr 2025 07:20:01 +0000 https://onlineengineeringnotes.com/?p=1712 1.1 Introduction 1.2 Purpose of Rate Analysis 1.3 Importance of Rate Analysis 1.4 Requirement of Rate Analysis 1.5 Factors affecting Rate Analysis References:

The post Rate Analysis in Civil Engineering appeared first on OnlineEngineeringNotes.

]]>
1.1 Introduction
  • Method of determining the rate per unit of particular item of work considering the cost and quantities of material, cost of labor, hire of tools, contractor profit etc. is known as rate analysis.
  • The rate of materials and labor vary from place to place and therefore the rate of different item of work also varies from place to place.

1.2 Purpose of Rate Analysis

  • To determine the actual cost per unit of item.
  • To determine the economical use of material.
  • To determine the cost of extra item which are not provided in contract document.
  • To examine the viability of rates offered by contractor.
  • To calculate the quantity of material and labor strength required for project planning.

1.3 Importance of Rate Analysis

  • It gives clear picture of the various types of labor and material required for completing the particular work.
  • Used to settle dispute between contractor and client.
  • Used for compensation by insurance.

1.4 Requirement of Rate Analysis

  • Correct information of the market rates of material.
  • Correct information of the rates of various categories of labor.
  • Output of labor.
  • Knowledge, rate of out turn of various types plants to be used in the construction work.
  • Upto date knowledge of construction work.

1.5 Factors affecting Rate Analysis

  • Quality of material.
  • Proportion of mortar.
  • Location of site.
  • Facilities available for transportation of labor and material to work site .
  • Overhead charge.
  • Availability of water connection.
  • Possibility of theft of losses.
  • Miscellaneous expenditure.

References:

  • Dutta, B.N. – Estimating and Costing in Civil Engineering, UBS Publishers, New Delhi.
  • CPWD (Central Public Works Department), India – Standard Schedule of Rates and Analysis of Rates.
  • IS 1200 – Indian Standard for Method of Measurement of Building and Civil Engineering Works, Bureau of Indian Standards (BIS).
  • Punmia, B.C. – Estimating and Costing, Laxmi Publications.
  • Building Estimation and Costing Notes – Department of Civil Engineering, Pokhara University.
  • MoUD Nepal – Standard Norms and Guidelines for Public Infrastructure Development Projects.

The post Rate Analysis in Civil Engineering appeared first on OnlineEngineeringNotes.

]]>
https://onlineengineeringnotes.com/2025/04/22/rate-analysis-in-civil-engineering/feed/ 0
Types of Estimates in Civil Engineering https://onlineengineeringnotes.com/2025/04/22/types-of-estimates-in-civil-engineering/ https://onlineengineeringnotes.com/2025/04/22/types-of-estimates-in-civil-engineering/#respond Tue, 22 Apr 2025 06:42:08 +0000 https://onlineengineeringnotes.com/?p=1708 1.1 Approximate Estimates Types: a. Unit rate estimate: b. Plinth area estimate: c. Cubic rate estimate: 1.2 Detailed Estimate Factors to be considered for preparation of detail estimate: 1.3 Revised Estimate 1.4 Supplementary Estimate It is also a detailed estimate and is prepared when additional work is required to supplement the original work. 1.5 Annual ... Read more

The post Types of Estimates in Civil Engineering appeared first on OnlineEngineeringNotes.

]]>
1.1 Approximate Estimates

  • Done to find out approximate cost in short time.
  • This estimate is prepared after preliminary surveying.
  • This estimate is prepared from practical knowledge and cost of similar works.

Types:

a. Unit rate estimate:

  • In this method all cost of a unit quantity such as per km for a highway, per meter for span of bridge, per bed for hospital etc. are considered first and the estimate is prepared by multiplying the cost per corresponding unit by the number of unit of the structure.
  • Buildings:
    • Per student for school/college
    • Per bed for hospital
    • Per seat for cinema hall
  • Road work:
    • Per Km
  • Bridge culvert:
    • Per meter length
  • Irrigation work:
    • Per Km of canal
    • Per hector of command area

b. Plinth area estimate:

  • In this method, plinth area rate of building is adopted from the cost of similar building having similar specification, height and construction in same locality.
  • Plinth area = Carpet area + Circulation area + Kitchen/Toilet + Wall

c. Cubic rate estimate:

  • This estimate is worked out on the basis of cubical content of the proposed building and then multiplying with rate per cubic content.
  • Estimate = Plinth area * height * cubical content rate

1.2 Detailed Estimate

  • It is an accurate estimate which contains very detailed data about project variable such as cost/quantity and price.
  • The dimension of each item are taken out correctly from drawing and quantities of each item are calculated, abstracted and billed.
  • 5-10% of estimated cost for unforeseen item and 2% of work charge establishment should be added.
  • This estimate is accompanied by:
    • Detailed report.
    • Detail specification for the execution of work.
    • Detailed drawing (plans, site plan, elevation etc.)
    • Calculation and design of various item such as beams, slabs etc.
    • Schedule of rates followed and premium if allowed.

Factors to be considered for preparation of detail estimate:

  • Quantity of materials.
  • Availability of materials.
  • Transportation of materials.
  • Location of site.
  • Availability of labor.

1.3 Revised Estimate

  • It is also a detailed estimate and is prepared when the original sanctioned detail exceeds by 5%.
  • Revised estimate is prepared:
    • When a sanctioned estimate is likely to exceed by more than 5%.
    • When the expenditure of work exceeds or is likely to exceeds by more than 10% of the administrative approval.
    • When there is material rate deviation from original proposal.
    • When sanction estimate is more than actual requirement.

1.4 Supplementary Estimate

It is also a detailed estimate and is prepared when additional work is required to supplement the original work.

1.5 Annual repair and maintenance estimate

In order to keep the structure in proper condition annual repair and maintenance are carried out. The estimate prepared for this purpose is known as annual repair and maintenance estimate.

1.6 Extension and improvement estimate

When some changes and extension are required to be made in the old work, a detailed estimate of extension and improvement work is carried out which is called as extension and improvement estimate.

1.7 Complete Estimate

  • In complete estimate following should be included:
    • Cost of land.
    • Cost of preliminary work.
    • Cost of preliminary design, drawing and estimate.
    • Cost of detailed design, estimate, specification and contract documents.
    • Cost of electricity, water supply and sanitary work.
    • Cost of design and supervision charges
    • Cost of external service.
    • Cost of repair and maintenance.

1.8 Split up of cost and building work

a. General split up:

  • Labor cost = 30-35% of total cost
  • Material cost = 65-70% of total cost

b. Stage wise breakup:

  • Construction below plinth level = 10-15% of total cost
  • Construction above plinth level = 85-90% of total cost

c. Activity wise breakup:

  • Foundation work = 17-18%
  • Brickwork/block work = 20%
  • Concreting and reinforcement steel = 15%
  • Door, windows and ventilation = 12%
  • Roof water proofing & finishing = 5%
  • Plastering = 5-6%
  • Flooring = 5%
  • Painting = 2-3%
  • Water supply and sanitation = 12-13%
  • Other work = 4-5%

References:

  • Dutta, B.N. – Estimating and Costing in Civil Engineering, UBS Publishers, New Delhi.
  • CPWD (Central Public Works Department), India – Standard Schedule of Rates and Analysis of Rates.
  • IS 1200 – Indian Standard for Method of Measurement of Building and Civil Engineering Works, Bureau of Indian Standards (BIS).
  • Punmia, B.C. – Estimating and Costing, Laxmi Publications.
  • Building Estimation and Costing Notes – Department of Civil Engineering, Pokhara University.
  • MoUD Nepal – Standard Norms and Guidelines for Public Infrastructure Development Projects.