Project and Program Management in Engineering

1.1 Difference between project and program

ProjectProgram
A temporary activity with a specific goal, scope and resources to deliver or create a unique output within a defined timeframe.A collection of related projects managed and coordinated to achieve strategic objective.
Limited scope with defined start and end dates.Broader in scope, involving multiple interconnected projects.
Short-term duration (Month to Year).Long-term duration involving several phases.
Independent from other project.Interdependent project, sharing resource and objective.
Project specific resources.Shared resources across the project.
Managed by individual project manager.Managed by multiple project manager.
Example: Building house or bridge.Example: Developing housing community.

1.2 Characteristics of project and program

  • Temporary: Project have a clear beginning and end.
  • Unique: Each project is different and has specific goals.
  • Defined scope: Project have clear boundaries and objective.
  • Resources: Project requires people, material and tools.
  • Goal oriented: Project aim to achieve specific outcomes.
  • Cross-functional: Involves people from different area.
  • Stakeholder: Involve people with an interest in project.
  • Integration: Different task are coordinated together.
  • Constraints: Project are limited by time, cost and quality.
  • Uncertainty: Project may face risk and unknowns.

1.3 Project life cycle

1. Conceptualization/Formulation phase

  • Ideas are brainstormed and evaluated to decide if the project is worth pursuing.
  • Rough plans are sketch out to see if the project is feasible.
  • Project objective, scope and initial plan are developed.

2. Design and development/Planning phase

  • Detailed project plan is created.
  • Tasks, timeline and resource are defined.
  • Risk analysis and mitigation strategies are developed.
  • Project team is assembled and roles are assigned.

3. Execution/Implementation phase

  • Actual work on the project begins.
  • Project team carries out the planned tasks and activities.
  • Project progress is monitored and adjustment are made if needed.

4. Finish/Terminating phase

  • Closing phase of project.
  • Project is formally closed and resources are released.
  • Lessons learned are documented for future improvements.

1.4 Introduction to planning, monitoring and control

  • Project planning: Process of defining project goals, creating a detailed roadmap.
  • Monitoring: Involves continuously tracking the progress of task and activities.
  • Control: Corrective action to keep the project on track.

1.5 Introduction to project planning tools

1. Gantt chart (Bar Chart)
  • It is a visual tool that shows the timeline of a projects tasks and activities.
  • Use horizontal bars to represent each task and their start and end dates.
  • Helps in scheduling, organizing and tracking project progress easily.

Use of Gantt chart for project planning and monitoring:

  • Task scheduling: Helps to create a timeline of task.
  • Dependencies: Shows which task need others to be done first (predecessor task).
  • Resource management: Helps to allocate resource effectively.
  • Critical path: Identifies the most critical tasks that could delay whole project.
  • Track progress: Helps monitor task completion and overall progress.

Resource planning and leveling by using Gantt chart:

  • Resource allocation: Helps to assign task to people and equipment.
  • Avoid overloading: Prevent giving too much work to one person.
  • Available resource: Show when resource is free to new tasks.
  • Balancing workload: Distribute work evenly among team member.
  • Resolve conflict: Resolves resource conflict between tasks.
2. Critical path method (CPM)
  • Project planning tool used to identify the sequence of tasks that determines project overall duration.

Use of CPM network for project planning and monitoring:

  • Identifying critical tasks: Helps to identify critical tasks that directly impacts project duration.
  • Efficient schedule: Helps create an optimized and realistic project timeline.
  • Early warning: Warns potential delay, allowing timely action.
  • Progress tracking: Monitors task completion to keep the project on track.
  • Project control: Helps manage and control the project progress effectively.
3. Milestone chart
  • It highlights key project events or goals as milestones.
  • Visual way to track progress.
4. Linked Bar chart
  • Display task as bars linked sequence.
  • Shows task duration and dependencies.
5. Program Evaluation and Review Technique (PERT)
  • Uses network diagram to represent task and their interdependencies.
  • Helps to identify risk in project.
6. Line of Balance
  • Used in projects with repetitive task such as construction.
  • Helps to plan and manage work by balancing resources.

1.6 Earned value analysis (EVA)

  • EVA measures amount of work in terms of cost and time.
  • Helps to predict future project performance based on current trends.
  • Shows project performance insight.

1. BCWS (Budgeted cost of work scheduled)

  • Planned cost for work scheduled to be completed.
  • Shows budgeted value for work.

2. ACWP (Actual cost of work performed)

  • Actual cost incurred in completing work to a specific date.
  • Shows actual expenses spent on complete work.

3. BCWP (Budgeted cost of work performed)

  • Value of the completed work as per the budget.
  • Shows planned cost of work that has been successfully finished.

1.7 Time-cost trade off

It is project management strategy where we decide between completing a project faster or saving cost by extending its duration.

1.8 Introduction to cost-control and technique audit

Cost control:

  • Process of managing and regulating project expenses.
  • Main objective is to ensure project stays within budget and avoid spending.
  • Methods involves:

a. Budget monitoring: Track expenses.

b. Variance analysis: Compare actual cost to planned cost.

Technical auditing:

  • Examination of project activities and outcomes to ensure they meet quality and technical standard.
  • Helps identify issue and improve project.

Reference:

Harold Kerzner (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling.
• PMI (2021). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – 7th Edition.
• Nebosh, Nepal Engineering Council Syllabus (2024). Engineering Professional Practice Notes.
• Civil Engineering Standard Method of Measurement (CESMM).
• Personal Class Notes & Presentations from Nepalese Engineering Institutions.

Leave a Comment