Methods of Estimation in Construction

1.1 Introduction and Importance of Estimation

  • Estimation is the process of predetermining of cost and size of any works. Also, in other words it is the process of calculating the quantity and cost of various item required in proposed work.
Importance of Estimation:
  • To fix budget for the proposed project.
  • To calculate required quantities of materials and number of labors for proposed projects.
  • To draw up a work schedule for proposed project.
  • To prepare tender document for the project.
  • To prepare valuation of land and building.
  • To fix up a completion period of the proposed project.

1.2 System of Unit

  • In general, the units of different item of work are based on following principle.
  • Mass, voluminous and thick work: L*B*H = m3
  • Shallow, thin and surface work (thickness < 75 mm): L*B = m2
  • Linear work/ long and thin works: L = Running meter
  • Pierce works/ job works: Number

1.3 Units of Measurement and Payment for items of work and Materials

S/NDescription of workUnits of measurementUnits of payment
1Earthwork  
aE/W in excavationm^3per m^3
bE/W in fillingm^3per m^3
cSurface dressingm^2per m^2
dQuarrying of stone or boulderm^3per m^3
eBlasting of rockm^3per m^3
fRock excavationm^3per m^3
2Brickwork  
aFlat brick soilingm^2per m^2
bBrickwork in foundationm^3per m^3
cBrickwork in cornice, capping, drip coursemper m
   
dHalf brick thin wallm^2per m^2
3Stonework  
aStone masonry, Random rubble masonry in wallsm^3per m^3
   
bStone slab in roofing, shelve etcm^2per m^2
cStone work in wall facing or liningm^2per m^2
   
4Concret work  
aPCC in foundationm^3per m^3
bLime concrete in foundationm^3per m^3
c75 mm thick pccm^2per m^2
dDPC (thickness specified)m^2per m^2
eRCC workm^3per m^3
fFormworkm^2per m^3
gPrecast PCC and RCCm^3per m^3
5Woodwork  
aWoodwork indoor and window framem^3 per  m^3
   
bWoodwork in rafters, beam, roof trussesm^3 per  m^3
   
cTimbering of trenches, boarding etc.m^2 per  m^2
   
dPlywood, window and door shuttersm^2 per  m^2
   
eWoodwork in partitionm^2 per  m^2
fBelliesm per  m
6Flooring work  
aSand fillingm^3 per  m^3
bMosaic flooringm^2 per  m^2
cMarble flooringm^2 per  m^2
dScreedm^2 per  m^2
eCement sand punningm^2 per  m^2
7Finishing work  
aPlaster workm^2 per  m^2
bPainting workm^2 per  m^2
cSkirtingm^2 per  m^2
dWhite washing, color washing, cement washingm^2 per  m^2
   
eDistemperingm^2 per  m^2
fEnamel painting on door and windowm^2 per  m^2
   
gPainting letters and figuresNo. per  No.
8Roofing work  
aTiled roofingm^2 per  m^2
bTile on ridge of roofm per  m
cCGI roofm^2 per  m^2
dAsbestos Cement (AC) sheet roofm^2 per  m^2
   
eStable roofing, timber roofingm^2 per  m^2
9Steel work  
aSteel reinforcementquintal per  quintal
bChannels, Angles, I-section, Beam etc.quintal per  quintal
   
cBending, binding of steel reinforcementquintal per  quintal
   
dIron work in trussquintal per  quintal
eIron gatem^2 per  m^2
fIron grill, collapsible gatem^2 per  m^2
gRolling Shutterm^2 per  m^2
hSteel door and windowm^2 per  m^2
iThreading in ironcm per  cm
jBoring holes in ironno. per  no.
10Miscellaneous items  
aCutting treesno. per  no.
bRailingm per  m
cPile drivingm per  m
dPipe layingm per  m
eSite clearance workm^2 per  m^2
fFurnitureno. per  no.
gFixing door and windowno. per  no.
hBituminous road surfacingm^2 per  m^2
iWater closet (W.C), Wash Basinno. per  no.
jElectric wiringpoint per  point
kGrouting work in crackm per  m
lGrouting work in roadm^2 per  m^2
11Material  
aBrickno. per  no.
bCementbag of 50 kg per  bag of 50 kg
cSandm^3 per  m^3
dAggregatem^3 per  m^3
eBrick, ballast, stone ballastm^3 per  m^3
fSteelquintal per  quintal
gBitumenton per  ton
hAc sheetm^2 per  m^2
iSwitches, plugs, bulbs etc.no. per  no.
jPipem per  m
kExplosive for blastingkg per  kg
lVarnish oilliter per  liter
mPaintliter per  liter

1.4 Requirement of Estimating

1. Drawings:

  • Drawings are required for the calculation of the quantities of the materials.
  • It shows plans, elevation, different section and other relevant detail with clear and complete dimensions.

2. Specification:

  • Specification describes the nature and class of the work, material to be used, workmanship and is very important for execution of work.

Types of specification:

a. General specification:

  • This gives a general idea about the nature, quality, class and material in general terms to be used invarious types of work.

b. Detailed specification:

  • This gives the detailed description of the various items of work laying down the quantities and qualities of material, their proportions, method of preparation, workmanship and execution of work.

3. Rates:

  • Rates are essential for the computation of estimate by multiplying quantities of materials with unit rates.
  • Rates include of various material to be used in the construction, cost of transport materials, wages of labor.

4. Method of measurement:

  • Updated mode of measurement for standard deduction or additions are also necessary to determine the correct quantities of work.

1.5 Methods of measurement of building and civil engineering works

1. Earthwork

  • Measurement in m3.
  • Includes throwing of excavated earth at least one meter clear of the edge of excavation.
  • Dressing or trimming, levelling or grading, ramming and consolidation thickness of each layer can be describe and include in the item of earthwork.
  • No separate measurement is taken for setting out works or site clearance.

2. Concrete work

  • Measurement in m3.
  • No deduction is done for opening upto 0.1 m2 (1 sq.ft).
  • No deduction shall be made for volume occupied by reinforcement.

3. Brickwork

  • Measurement in m3.
  • Deduction for doors, windows and other opening including lintel.
  • Different kinds and classes of brickwork shall be taken under separate item.

4. Plastering work

  • Measurement in m2.
  • Plastering of all roofs ceiling, walls etc shall be measured under separate item.
  • No deduction is done for joints, beam upto 0.5 sq.m or 5 sq.ft.

5. Painting work

  • Measurement in m2.
  • Different types of surfaces such as steel, wood, concrete etc shall be taken under separate item.

1.6 Subheads of various item of work

  • Earthwork
  • Concrete work (a. PCC work b. RCC work)
  • Masonry work (a. Brick work b. Stone work)
  • Wood work
  • Flooring work
  • Finishing work (a. Cement plaster work b. Painting work c. Roofing work)

1.7 Various Methods of Taking Out Quantities

1. Centre Line Method:

  • This method is suitable offsets are symmetrical and the building is more of less rectangular in shape.
  • According to this method, total length of centerline of wall is calculated and this length is multiply by corresponding breadth and height of item of work to find its quantity.

2. Long Wall and Short Wall Method:

  • According to this method, the long wall is consider first and the wall perpendicular to this wall is consider as short wall.
  • The long wall is measured from out to out and the short wall is measured from in to in. After, finding the length of wall, this length is multiplied by corresponding breadth and height of item of work to find quantity of that item.
  • Used for building having unsymmetrical layouts, wall for varying thickness, height etc.
  • Upto plinth level from footing we can use this method to estimate the quantity.

3. Crossing Method:

  • In this method, length and breadth of the masonry walls at plinth level are taken (internal dimension of room + thickness of wall) for calculating quantities.
  • The center line length is obtain by calculating the overall perimeter of building and subtracting four times thickness of wall on it.

1.8 Abstracting Bills of Quantities

  • A bill of quantities is a document used in tendering process which includes the materials, parts and labor with respect to their cost.
  • It is also a detail term and condition of the construction or repair contract and itemizes all work to enable a contractor to price the work for which he/she is bidding.

References:

  • Dutta, B.N. – Estimating and Costing in Civil Engineering, UBS Publishers, New Delhi.
  • CPWD (Central Public Works Department), India – Standard Schedule of Rates and Analysis of Rates.
  • IS 1200 – Indian Standard for Method of Measurement of Building and Civil Engineering Works, Bureau of Indian Standards (BIS).
  • Punmia, B.C. – Estimating and Costing, Laxmi Publications.
  • Building Estimation and Costing Notes – Department of Civil Engineering, Pokhara University.
  • MoUD Nepal – Standard Norms and Guidelines for Public Infrastructure Development Projects.

Leave a Comment